 DSC Project, Jail Alley Wall - Fredericksburg, VA. January 2008. 

Fredericksburg VA, Jail Alley Wall. Before (12/07). This photo doesn't even begin to show the compicated site access issues!
Fredericksburg VA, Jail Alley Wall. Before (12/07). This photo doesn't even begin to show the compicated site access issues!
Viewed: 1703 times.

Fredericksburg VA, Jail Alley Wall. Before (12/07). Note utilities!
Fredericksburg VA, Jail Alley Wall. Before (12/07). Note utilities!
Viewed: 1530 times.

Fredericksburg VA, Jail Alley Wall. Before (12/07). Note proximity of a/c units, utility pole guy wire, access drive above to remain open at all times.
Fredericksburg VA, Jail Alley Wall. Before (12/07). Note proximity of a/c units, utility pole guy wire, access drive above to remain open at all times.
Viewed: 1499 times.

Fredericksburg VA, Jail Alley Wall. Before (12/07). Alley also to remain open at all times for neighbors to access garages and businesses. Alley is one-way, to get backhoe from top of wall to bottom requires a trip around the block!
Fredericksburg VA, Jail Alley Wall. Before (12/07). Alley also to remain open at all times for neighbors to access garages and businesses. Alley is one-way, to get backhoe from top of wall to bottom requires a trip around the block!
Viewed: 5080 times.

Fredericksburg VA, Jail Alley Wall. Before (12/07). Coordination with another contractor on site who is repairing cracks and waterproofing the concrete steps, wall and walkway.
Fredericksburg VA, Jail Alley Wall. Before (12/07). Coordination with another contractor on site who is repairing cracks and waterproofing the concrete steps, wall and walkway.
Viewed: 2142 times.

Fredericksburg VA, Jail Alley Wall. Day one, dismantling. Because there is no space on site for stockpiling, the soil is loaded onto one-ton dump trucks (due to narrow alley access) and taken off site until needed again. Stone is laid out in the only available space on site for staging, a narrow sidewalk owned by the city.
Fredericksburg VA, Jail Alley Wall. Day one, dismantling. Because there is no space on site for stockpiling, the soil is loaded onto one-ton dump trucks (due to narrow alley access) and taken off site until needed again. Stone is laid out in the only available space on site for staging, a narrow sidewalk owned by the city.
Viewed: 1660 times.

Fredericksburg VA, Jail Alley Wall. Day 3, forms set. For gravity walls with a vertical front face, the required base width is a 1 to .6 ratio, in other words 10 feet tall = 6 feet base width.
Fredericksburg VA, Jail Alley Wall. Day 3, forms set. For gravity walls with a vertical front face, the required base width is a 1 to .6 ratio, in other words 10 feet tall = 6 feet base width.
Viewed: 1563 times.

Fredericksburg VA, Jail Alley Wall. Day 4. Back slope is sheeted to prevent slumping from forcast rain and snow.
Fredericksburg VA, Jail Alley Wall. Day 4. Back slope is sheeted to prevent slumping from forcast rain and snow.
Viewed: 1474 times.

Fredericksburg VA, Jail Alley Wall. Day 9, sleet and snow today - work called off.
Fredericksburg VA, Jail Alley Wall. Day 9, sleet and snow today - work called off.
Viewed: 1635 times.

Fredericksburg VA, Jail Alley Wall. Day 10, morning.
Fredericksburg VA, Jail Alley Wall. Day 10, morning.
Viewed: 1580 times.

Fredericksburg VA, Jail Alley Wall. Day 10, morning.
Fredericksburg VA, Jail Alley Wall. Day 10, morning.
Viewed: 1459 times.

Fredericksburg VA, Jail Alley Wall. Day 10, morning.
Fredericksburg VA, Jail Alley Wall. Day 10, morning.
Viewed: 1696 times.