|
|
Contractor staff discussing height and layout of new drystone approach ramps to be installed by the Conservancy.
Date: 06/13/2008
Views: 802
|
|
This dry-laid (later mortar-pointed) stone pier was a later addition to the bridge when it started to sag.
Date: 03/24/2006
Views: 864
|
|
|
Date: 02/27/2009
Views: 764
|
|
The south abutment. Notice how much of the stream bank has eroded away.
Date: 03/24/2006
Views: 794
|
|
|
The abutments were built dry-laid, but mortar-pointed in the mid-to-late 1900's.
Date: 03/24/2006
Views: 785
|
|
North abutment, east wing wall. Preparation for repairs. 3/30/09.
Date: 03/30/2009
Views: 808
|
|
|
North abutment, east approach ramp wall, awaiting cover stones. 3/27/09.
Date: 03/27/2009
Views: 790
|
|
North abutment, west approach ramp wall, awaiting cover stones. 3/27/09.
Date: 03/27/2009
Views: 783
|
|
|
North Abutment approach completed. 4/1/09.
Date: 04/08/2009
Views: 738
|
|
South Abutment, east approach ramp wall.
Date: 03/30/2009
Views: 742
|
|
|
South Abutment, west approach ramp wall.
Date: 03/30/2009
Views: 821
|
|
South Abutment approach completed. 4/1/09.
Date: 04/08/2009
Views: 856
|